In “The Goal: A Process of Ongoing Improvement”, Eliyahu Goldratt aims to tackle the problems which the production industries face and challenges the common business practices by using the ‘Theory of Constraints’.
The main
character Alex Rogo, a manager at a production plant is given three months to save
his plant. The plant is facing heavy losses as most of the orders did not ship
on time and had to be expedited and the inventory was piling up. Alex takes
help of his old physics teacher Jonah who uses the Socratic approach to help
him.
Jonah asks
Alex to ponder about the ultimate goal of the company. Alex realises that the
goal of the company is to make money and all the actions which help the plant
in making money are productive. Jonah further defines 3 terms for measurements:
Throughput – “The rate at which system generates money through sales”. Inventory
- “The money that the system has invested in purchasing things which it intends
to sell." Operational expense - “The money the system spends in order to
turn inventory into throughput." Everything in the plant can be classified
by these 3 terms. The goal is to increase throughput while decreasing inventory
and operational expenses. Jonah then asks Alex to find the bottlenecks i.e. the
machines with capacity less than the demand placed on it in the plant. He
further states that the plant can increase productivity only by increasing the
capacity of the bottleneck operations. Alex identifies the bottlenecks and
works out on a detailed plan to keep the bottlenecks fully utilized. Also, a
plan is made to release the materials only when needed to reduce the work in
process inventory.
To further
improve productivity Jonah recommends to reduce the batch size by half. Alex
realises that this will help to reduce the total lead time by decreasing the
queue and wait time and thus they can respond faster to market demands.
Also, he finds out the flaws in the old accounting policies particularly in
finding the cost per part.
Alex’s plant is now making huge
profits and as a result, he is promoted. Alex’s team formulates a five step
Process of On-Going Improvement. These are 1) Identify the system’s
bottlenecks. 2) Decide how to exploit those bottlenecks. 3) Subordinate
every other decision to 'step two decisions.’ 4) Elevate the systems’
bottlenecks. 5) if, in a previous step, a bottleneck has been broken, go
back to the beginning. Alex finally realises that as a manager he must learn to
solve his own problems without anybody’s help by asking suitable questions.
My experience with the use of ‘Theory of
Constraints’
I worked at a construction site
for some time during my tenure at an EPC company. We faced the problem that the
pipe rack construction was lagging behind schedule. Pipe racks are steel framed
structures used to support pipes and cables. It consists of different members
such as beams, columns, struts, bracings etc. We procured the material from
vendors and then and welded them at site. The vendors released the material in
batches and payment was made based on the tonnage of material received, while
our firm received payment from the client based on our overall progress. Even
though the vendors dispatched the material on time still we lagged behind
schedule and our progress was low which severely impacted our cash flow.
The goal here was to complete
the pipe rack construction as early as possible. Upon talking with the
construction workers, we realised that the vendors used to send the larger
parts which were easier to fabricate and also had higher tonnage first to
receive early and a higher percentage of payment. Also, the site workers had to
segregate the received parts which took up a lot of time. Without receiving
some of the smaller matching parts which had low tonnage the workers were
unable to complete the structure which also slowed our progress. We were paying
the vendors but were not receiving payment from client as we showed low
progress.
To remove these constraints, we had
a meeting with the vendors and it was decided that during each dispatch the
vendor would send all different types of parts in definite proportions. Also,
all these parts are to be segregated at the vendor’s shop itself. We had to pay
the vendors more but eventually it significantly improved construction time for
pipe rack which showed in our overall progress.
No comments:
Post a Comment